The customer required an accelerated delivery schedule for seven structures, aiming to minimize construction activities during the peak winter period. The project, valued at $0.9 million USD and involving four unique designs, was successfully completed within 19 weeks ARO. All key design documents—including Fabrication, Assembly, BOM drawings, PLS-Pole “.bak” files, and cage assembly drawings—were submitted within the first 2 weeks, followed by customer approval in another 2 weeks. Manufacturing of the entire order was completed in 3 weeks, after which the shipment proceeded with 6 weeks of sailing from the Indian port to the U.S. port and an additional 1 week of transit to the customer site.